Tehaleh's Road to SR 162 Is Being Built From the Bottom Up

November 12, 2026

At the top of the hill, the new road from Tehaleh has existed for nearly two years. In December 2024, The News Tribune reported that the first finished phase linked Falling Water Boulevard to Tehaleh Boulevard. The downhill connection and the river bridge were left for later phases. At the bottom of the hill, where 128th Street East meets SR 162 at McMillin, a roundabout is taking shape and traffic has already been moved around it. Between those two points, work on the slope has stopped.

That order matters for anyone who drives between Tehaleh and the valley. The pieces at the bottom of the route are on fixed construction schedules. The road down the hill, the piece that connects them, is waiting on a federal permit. So the roundabout, the 128th Street East widening and the new lane patterns will be in Tehaleh drivers' commutes for more than a year before the road they were built to serve opens.

What Pierce County Calls It, and What Already Exists

Pierce County's official name for the project is "New Rhodes Lake Road East - SR 162 to Falling Water Blvd." The county's project page is the official place to check its status. Tehaleh's own Summer 2026 Blueprint links to that page for Rhodes Lake Road updates.

The finished corridor is planned as a four-lane highway from Tehaleh Boulevard down to SR 162 at McMillin, with a truck climbing lane and a mixed-use path. The plan also includes a second bridge over the Puyallup River, a wider 128th Street East, and McCutchen Road realigned to meet the new highway. Those details come from the SR162 Community Group, a community advocacy group focused on transportation in East Pierce County. It has posted the most frequent public updates on the project.

By February 2026, the group reported that the first construction phase of the new corridor was finished, with much of the highway excavation done "from the Taheleh end to near the bottom of the hill." The upper part of the hill has been cut. The bottom of the slope and the river crossing have not.

The Hold Is at the River

The February update tied the stoppage to environmental review of the roadway's crossing over the Puyallup River. At the time, the group expected construction to resume in early 2026. In its August 5 update, the group said the final federal permit was expected in October and moved its completion estimate to the first quarter of 2028. Its September 14 update described the status this way:

"Construction is on hold awaiting a final federal permit, expected any time now, Without unforseen delays, a corridor connection from SR162 to the Bonney Lake plateau should be operational by the middle of 2028, however only 2 lanes will cross the Puyallup River until the second bridge is added."

That update also said the bridge portion "is funded and nearly permitted," with no construction timeline announced.

Federal fisheries records describe the bridge design. A June 2025 Biological Opinion from NOAA Fisheries covers the "Pierce County-New Rhodes Lake Road East Bridge," a crossing the U.S. Army Corps of Engineers proposes to permit. Today, the 128th St. E./McCutcheon Rd. E. bridge over the Puyallup carries one lane each way. Under the plan, that bridge would be widened for a pedestrian pathway and would carry two lanes in one direction. A new bridge just north of it would carry two lanes in the other direction, for four lanes across the two bridges.

So even after the hill road opens, the river crossing will have only two lanes until the second bridge is built. Of all the pieces in the project, the bridge is the one that most limits how much the new road can carry.

At McMillin, the Change Is Already in the Pavement

The valley end of the project is already under construction. The roundabout at SR 162 and 128th Street East is the only one on this corridor with funding, according to the SR162 Community Group. By its September 13 update, traffic had been shifted to the east side of SR 162, onto what will become the east half of the roundabout. New signals were in, and the work-zone speed limit had dropped to 40 mph between 136th Street East and Military Road. The group expects that speed limit to stay after the roundabout is finished.

The group's October 13 update describes how the interim roundabout will work once this phase is finished:

  1. The roundabout itself: one lane, with the center lane closed until the final phase and the extra lane striped off.
  2. Southbound SR 162: two approach lanes. The right lane goes straight or turns right onto 128th Street East. The left lane goes straight or enters the roundabout. The two lanes merge into one before 136th Street East.
  3. Northbound SR 162: a single lane enters the roundabout.
  4. Westbound 128th Street East, coming from McCutchen: two approach lanes. The right lane merges northbound onto SR 162, and the left lane enters the roundabout.
  5. Eastbound 128th Street East: one lane approaching SR 162 across the railroad tracks. The railroad crossing work was projected to finish by the end of October 2026.

The same update says the interim phase "will not be completed entirely until June 2027." The group's September roadway update puts roundabout completion in spring 2027. It also names the next phase drivers will see: widening 128th Street East between the Puyallup River and SR 162 to two lanes in each direction. That work is projected to start in the first quarter of 2027 and to be finished when the highway to Tehaleh opens. Property acquisition along 128th Street East was still underway in September.

The Projected Sequence, Piece by Piece

The first two rows are finished work. Every future date below is a projection from the SR162 Community Group's updates, and none is a confirmed opening date.

Piece of the route Status in the latest update Milestone
Falling Water Blvd to Tehaleh Blvd Built in an earlier phase Done, per The News Tribune in Dec. 2024
Hill excavation from the Tehaleh end Phase 1 completed Done by Feb. 2026
SR 162/128th St E roundabout Interim single-lane layout under construction Spring 2027; interim phase fully complete by June 2027
128th St E widening, river to SR 162 Property acquisition underway Start in Q1 2027; finish by highway opening
Hill road from Tehaleh Blvd to SR 162 On hold for a final federal permit Opening in Q1 2028; corridor operational by mid-2028
Second Puyallup River bridge Funded and nearly permitted No construction timeline announced

The roundabout is projected to be finished in 2027, the 128th Street East widening to start in 2027 and finish alongside the hill road in 2028. Two lanes over the river carry the load until a bridge with no announced start date is built.

Why the Developer's Agreement Sets the Pace

Tehaleh's developer is building this as a county road. Tehaleh's Future Plans page explains that a Development Agreement with Pierce County requires the community to offset its traffic impacts as it grows. For Phase 1, Tehaleh funded and built $26.1 million in road work on SR 410 intersections and the expansion of 198th Street. Tehaleh puts that at about $10,000 per home. By its comparison, the per-home traffic impact fees are $2,276 in Sumner, $3,191 in Bonney Lake and $2,149 in Orting.

Phase 2 is larger. The same page says the per-home mitigation cost will likely double, funding up to $180 million in road improvements, including New Rhodes Lake Road East and work on SR 162 and nearby roads. The News Tribune described the project as a $150 million developer-funded effort under the county agreement. Because the money is committed through that agreement, the schedule depends mostly on permits.

The Phase 1 numbers also explain the route Tehaleh uses now. That $26.1 million went into the SR 410 side of the plateau. When ground broke on Rhodes Lake Road East in 2023, Tehaleh presented the new SR 162 connection as an alternative to the existing route toward SR 410. Until the hill road opens, SR 410 remains Tehaleh's built connection to the valley.

What the Extra Time Gives the Valley Floor

The SR162 Community Group sees one benefit in the delay. Its August update said the later date gives more time for a possible extension of 128th Street East from Tehaleh toward South Hill, which is still in the study phase. It also pushes back the added traffic on SR 162. The group notes that Pierce County is studying a new road up the hillside to South Hill, and that WSDOT's SR 162 study recommends more roundabouts. None of that work is funded. The proposed roundabouts would sit at Pioneer Road, 96th Street East in Alderton, 136th Street East at the McMillin industrial park, and 149th Street East at High Cedars.

For a Tehaleh driver heading toward Orting this winter, the change comes at the bottom of the hill first: a 40 mph work zone, a single-lane roundabout and a lane merge before 136th Street East. The road from Tehaleh Boulevard down to that roundabout is projected to open in 2028, and the county's project page is where an official start will be posted.

At Jesse Misener, we follow road projects like New Rhodes Lake Road East because they change how a Tehaleh address works day to day, and that affects how a home should be presented and priced. If you're thinking about a move on the plateau and want to know how the 2027 and 2028 milestones fit your timing, let's talk about it in a consult.